Controlled blasting and temporary Fernie Road intersection closure planned
Main Roads Western Australia has provided advance notice of upcoming works on the Toodyay Road Upgrade project, including controlled drill and blast activities from early December 2026 and a temporary closure of the Toodyay Road and Fernie Road intersection from January 2027.
Drill and blast works
Controlled blasting is required to remove hard rock before further excavation works can continue as part of the Toodyay Road realignment.
Blasting will occur between Lovers Lane and Strahan Road, and between Sandplain Road and Clackline-Toodyay Road. Works are scheduled from Monday to Friday, commencing in early December and continuing until 23 December 2026. They will resume in January 2027 following the Christmas and New Year site shutdown.
For safety, Toodyay Road between Lovers Lane and Strahan Road will be temporarily closed in both directions for up to 20 minutes while each blast is undertaken. Blasts are expected to occur once per day between 12pm and 3pm. Road users are encouraged to plan ahead, allow additional travel time and, where possible, avoid travelling through the blasting area during the weekday blasting timeframe.
Toodyay Road and Fernie Road intersection closure
From January 2027, access between Toodyay Road and Fernie Road will be temporarily closed for approximately four to six weeks while Main Roads WA upgrades the intersection. The works will improve heavy-vehicle turning capacity and include new eastbound and westbound passing lanes to provide safer overtaking opportunities.
A signed detour via Salt Valley Road will be in place, with traffic management and signage provided at the Toodyay Road/Fernie Road intersection, Chitty Road and Hoddy Well Road. Variable Message Boards will also help guide road users. The specific commencement date will be confirmed by Main Roads WA closer to implementation.
Residents and businesses along the detour route are asked to be mindful of increased vehicle movements, take care when travelling and remain vigilant when entering or leaving driveways.
Traffic management changes
Main Roads WA also plans to introduce longer shuttle traffic flows across five-kilometre sections of Toodyay Road. While this may result in longer waits at individual stop points, it will reduce the number of stopping points overall and assist with speed management and safety through work areas.