Notification - Re-seal Works

Published on Thursday, 21 April 2022 at 4:09:04 PM

Please be advised that these works have since been postponed until further notice. More information can be found here.

The Shire of Toodyay wishes to advise that re-seal works on Bejoording Road will commence on 9 May 2022, with completion expected by 16 May 2022. The total road length to be re-sealed is 9.3 kilometres.

Traffic management will be in place. Please observe traffic management measures on site and drive according to conditions. 

Completion of these works is subject to weather permitting.

The Shire apologises for any inconvenience caused by these works and appreciates your cooperation.

Location of Works

Location of Re-seal Works